The Makler- und Bauträgerverordnung (MaBV) is designed to stop a developer receiving money before the work is done. As a rule, payments are only allowed once certain conditions are met: the contract is valid, the buyer's priority notice (Auflassungsvormerkung) is registered, release from the developer's bank charges is secured and building permission has been granted. After that, payment is made in no more than seven instalments linked to construction stages. A typical mistake is paying a developer's invoice without checking how far the building has actually progressed. Anything paid beyond the work done may be lost if the developer becomes insolvent.
Makler- und Bauträgerverordnung (MaBV): Die Makler- und Bauträgerverordnung regelt unter anderem, unter welchen Voraussetzungen und in welchen Raten ein Bauträger Zahlungen des Käufers entgegennehmen darf.